BESS case study: 1.2 MW Malaysian extrusion plant, RM 670k projected annual saving.

This BESS case study covers a Peninsular Malaysia extrusion site on TNB Bukan Domestik ToU. A recorded 676 kW Maximum Demand, driven by a recurring 20:00–22:00 evening peak, set the bill. UniBess proposed a phased BESS: a 250 kW pilot to validate the load, then a 2.5 MW deployment for the headline saving. Site anonymised. Figures from the actual sizing study.

The load, read

Two peaks set the bill. Both capped to target.

kW MD shave target Morning surge Evening peak 00:0008:0014:0020:0024:00 Recorded load With BESS, capped to target
47 days of interval data showed a morning start-up surge and a sharp evening peak. The battery discharges through both so metered demand holds at the contracted MD-shave target (blue), capturing the saving every billing cycle.
01

The headline numbers

RM 670k
Estimated annual saving
Phase 2 full deployment
~576 kW
MD reduction target
peak window 14:00 to 22:00
5.22 MWh
BESS capacity
20 cabinets, 8-hour discharge
6 to 7 yr
Simple payback
CAPEX route
02

Site context

Sector:

Plastics extrusion (anonymised).

Connection:

400 V, 3 Phase + Neutral.

Tariff:

TNB Bukan Domestik Time-of-Use (B2).

Recorded MD:

676 kW (Dec 2025 to Feb 2026 reference period).

Operating pattern:

Continuous operations with a recurring evening peak surge between 20:00 and 22:00.

Reference month bill:

approx. RM 151,500 (Caj Semasa, single sample month).

03

What the load data revealed

UniBess collected 47 valid days of 15-minute interval data over a 12-week period. Four findings shaped the BESS sizing:

Morning surge.

Daily spikes above 1,300 kW between 08:30 and 10:00, outside the MD target window we focus on first.

22:00 load step.

At exactly 22:00 the load shot vertically past 1,000 kW, a start-up coinciding with the off-peak boundary.

Stable baseline.

During the critical 14:00 to 22:00 peak window, average load was remarkably consistent at approximately 485 kW.

Tail-end spikes.

Over 60% of billable MD spikes (500 to 676 kW) erupted in the final 90 minutes of peak hours (20:30 to 21:59).

Conclusion:

target the 676 kW evening hill first with a pilot, then expand to full peak coverage.

04

The two-phase design

Phase 1

250 kW / 522 kWh pilot

Right-sized pilot targeting the recurring 20:00 to 22:00 evening spike. 2 cabinets, 8 weeks of operational data, validates EMS dispatch logic.

  • MD reduction target: approx. 73 kW.
  • Estimated annual saving: approx. RM 85,000.
  • Phase 1 de-risks Phase 2: if the pilot underperforms, no Phase 2 capex is triggered.
  • Indicative CAPEX: approx. RM 1.25 M, or lease at approx. RM 18,500/mo.
Phase 2

2,500 kW / 5,220 kWh full

20 cabinets in AC-coupled cluster, 8-hour continuous dispatch across the full 14:00 to 22:00 peak window. Drops MD from 676 kW down to a 100 kW target.

  • MD reduction target: approx. 576 kW continuous shaving (676 → 100 kW).
  • Estimated annual saving: approx. RM 670,000.
  • Plus approx. RM 30,000/year of energy arbitrage on the peak/off-peak delta (additional upside).
  • Indicative CAPEX: approx. RM 11 M, or lease at approx. RM 142,000/mo.
05

Performance commitments in the contract

  • ≥ 60 kW guaranteed monthly MD reduction (Phase 1, in the 20:00 to 22:00 setting interval).
  • ≥ 500 kW guaranteed monthly MD reduction (Phase 2, across the full 14:00 to 22:00 peak window).
  • ≥ 97% availability per measurement year, peak hours.
  • 85% to 78% round-trip efficiency, Year 0 to Year 10.
  • ≥ 70% capacity retention by Year 10 of nameplate.
  • Measurement: rolling 12-month average against a Counterfactual MD baseline (12 months pre-commissioning, ±10% Reference Load Envelope).
06

Why phased, not single-shot

The temptation with a project like this is to skip the pilot and go straight to Phase 2. We argued against that for three reasons:

Load profile validation.

47 days of data is enough to size; it's not enough to trust the size. Phase 1 puts hardware on site running real dispatch, and we can re-run sizing against actual telemetry before we commit Phase 2 capex.

EMS tuning is site-specific.

Dispatch parameters get tuned for at least 4 to 6 weeks in real operations. Better to do that on a 250 kW system than a 2.5 MW one.

Capex de-risking for the client.

If Phase 1 underperforms the model, the client has spent RM 1.25 M, not RM 11 M. If it meets target, Phase 2 unlocks with strong confidence.

Phased delivery is how serious BESS gets built. Anyone offering a turnkey 5 MWh deployment on a never-seen-before load profile is selling you risk, not engineering.

Have a site that looks like this one?

Send us TNB invoices (any 3 months) and a brief site description. We'll respond within one business day with a first-cut sizing estimate and indicative payback for your specific situation.

Send the data →