The line items in a BESS quote
A complete BESS quote for a Malaysian factory splits into hardware, integration, grid connection, commissioning and long-term service. Hardware covers battery cabinets or containers, the power conversion system (PCS), the energy management system (EMS), fire suppression and cooling. Integration covers civil works, cabling, switchgear and transformer interfaces.
Grid connection covers TNB application support, the single-line diagram and protection settings. Service covers monitoring, preventive maintenance and warranty administration. Ask for each as a separate line, with SST shown apart and the currency basis stated for imported equipment.
Five energy figures every BESS proposal should separate
One capacity number hides the gap between what the battery holds and what reaches your switchboard. Ask for all five.
| Figure | What it means | Why it matters |
|---|---|---|
| Power (kW) | Maximum charge or discharge rate at the AC terminals | Sets how many kW of peak the system shaves |
| Nominal energy (kWh) | Energy rating of the cells on the DC side | The headline number, not the usable one |
| Usable energy (kWh) | Nominal energy inside the allowed state-of-charge window | Sets how long the battery holds the peak |
| Deliverable AC energy (kWh) | Usable energy after PCS, transformer and auxiliary losses | What your load receives |
| Energy after degradation | Deliverable energy in the final warranty year | Sizing must still meet the MD target then |
Then check the savings assumptions behind the numbers:
- Tariff basis. Tariff category, rates and peak window used, with the date of the tariff schedule.
- MD target. The kW cap per month and the interval data behind it.
- Efficiency. Round-trip efficiency at the AC meter, including auxiliary loads for cooling and controls.
- Degradation. Expected capacity by year and the cycles per day assumed.
- Operating window. State-of-charge limits, recharge time before the next peak and any reserve held for backup.
- Controls. How the EMS forecasts and dispatches, and how it reacts to an unexpected spike.
Compare cost per kWh delivered, not cost per kWh installed
Two quotes with the same price per nominal kWh deliver different value when one offers a wider usable window, higher efficiency or slower degradation. Divide total lifetime cost, service included, by the AC energy the system delivers over the warranty term. The lower figure wins.
For peak shaving, add a second test: cost per kW of Maximum Demand reduction held for the full term. At RM 97.06/kW a month on the Medium Voltage ToU tariff, each kW held for ten years is worth about RM 11,650 before discounting.
What a UniBess proposal shows
Every UniBess proposal lists power, nominal, usable and deliverable energy, the degradation curve, the tariff basis and the EMS logic, with equipment and services priced as separate lines.
Common questions
What should a transparent BESS proposal in Malaysia include?
Power in kW, nominal, usable and deliverable AC energy, capacity after degradation, the tariff and peak window used, the Maximum Demand target, round-trip efficiency including auxiliaries, the EMS dispatch logic, and separate prices for equipment, installation, grid connection and service.
Why is usable BESS capacity lower than nominal capacity?
Batteries operate inside a state-of-charge window to protect cell life, and every conversion step loses energy. Usable energy is the share inside the window. Deliverable AC energy is lower again after inverter, transformer and auxiliary losses.
Does UniBess share a cost breakdown before contract?
Yes. Equipment, installation, grid connection, commissioning and service appear as separate lines in the proposal, with SST and currency assumptions stated.
Get a BESS cost breakdown for your site
Send three months of TNB bills and your interval data. We return a sizing with every line item and assumption in writing.