What the System Marginal Price is
The System Marginal Price (SMP) is the energy price of the most expensive generator dispatched to meet demand in each half-hour period in Peninsular Malaysia. The Single Buyer, which manages electricity procurement for the Peninsula, publishes half-hourly actual and forecast SMP plus a monthly average.
SMP moves with fuel prices, demand and the generation mix. It is a wholesale figure, not the tariff a factory pays TNB, which adds capacity, network and retail charges on top of energy.
| Period | Average SMP | Source |
|---|---|---|
| 2021, full year | 16.95 sen/kWh | Single Buyer MESI factsheet |
| 2022, full year | 24.60 sen/kWh | Single Buyer MESI factsheet |
| 1 Jan to 8 Apr 2024 | 20.46 sen/kWh | The Edge, citing Single Buyer |
| January 2026, 07:00 to 19:00 | RM 0.1911/kWh | Single Buyer, revised |
| February 2026, 07:00 to 19:00 | RM 0.1893/kWh | Single Buyer, revised |
Where the System Marginal Price shows up for a Malaysian business
Three links tie business decisions to SMP.
- Solar ATAP: from 1 January 2026, Solar ATAP replaced net energy metering. Non-domestic sites receive bill credits for exported solar at the average SMP issued by the Single Buyer.
- Corporate green power: the Energy Commission points buyers and developers to the Single Buyer forecast SMP as a guide for setting the strike price in corporate green power agreements.
- Dispatch signal: the Single Buyer uses SMP in scheduling and dispatch, and its half-hourly data shows when the grid is tight and power is expensive.
What SMP means for battery storage
For a factory with rooftop solar, SMP sets the value of each exported kWh, around 19 sen in early 2026. The same kWh stored in a battery and used in the TNB peak window offsets 31.32 sen/kWh of energy on the Medium Voltage ToU tariff, and helps hold down the Maximum Demand charge. The gap between the two decides whether solar battery storage pays.
For a factory without solar, SMP plays no direct role in the bill, and peak shaving against the TNB Maximum Demand charge drives the BESS business case.
Check the live figure
SMP changes every half hour, and the monthly average moves with gas and coal prices. Use the latest Single Buyer data when you model solar export or storage. Figures above as published by the sources listed.
Common questions
What is the system marginal price in Malaysia?
It is the energy price of the most expensive generator dispatched to meet demand in a half-hour period in Peninsular Malaysia, published by the Single Buyer as half-hourly and monthly average figures.
How much is the SMP in 2026?
The Single Buyer reported a revised average SMP of RM 0.1911/kWh for January 2026 and RM 0.1893/kWh for February 2026, measured from 07:00 to 19:00. Check the Single Buyer website for the latest month.
How does SMP affect Solar ATAP?
Under Solar ATAP, non-domestic consumers receive credits for exported solar at the average SMP. Storing surplus solar in a battery and using it in the TNB peak window often returns more per kWh than exporting it.
Test solar storage against SMP